The successfully launched Project at Volvo is progressing well. Our team is on schedule so far. On Monday 18th August 2014 was the official start of TCT Tesic's next big project.
This time it has taken us to a huge dismantling job at Volvo Sweden. Within four months TCT's 12 man crew has been to dismantle, pack and load a HWS ZFA Moulding Line (870 x 870 x 250/250mm; 210 Forms p. hour), WEBAC Sand plant(130 t/h), complete Core shop and a DISA CT-6 Shotblast machine.
Later on the equipment needs to be re-assembled at customers site.
The first containers have already been loaded and so far the customer as well as Volvo are very satsfied, which is very important