A significant capital project at Waupaca Foundry Plant 4, Marinette, WI ductile iron foundry, was installed on budget in 16 days over the recent holiday shutdown. A new conveyor system replaces a 30-year-old vibratory system and is expected to improve its maintenance downtime by over 50%.
The vibrating shaker system that transports gating and sprue material was replaced with a state-of-the-art conveyor system in the foundry’s ductile casting shakeout department. The new conveyance system from Magaldi is required extensive renovation downstream of six iron casting sorting tables.
“Preparation and planning were critical leading into the project due to the scope of work required given the defined shutdown install window,” said Jarrod Osborn, vice president of manufacturing engineering for Waupaca Foundry.
Waupaca engineering teams started planning for the capital project in 2022 to fit the longer conveyor system at the end of the molding lines within the current manufacturing footprint. The legacy vibratory shaker was replaced with two parallel Magaldi Superbelt conveyor systems designed to offset maintenance and energy costs, eliminate iron casting jams, abate noise, and decrease dust exposure.
The engineering team identified nearly 300 action items to complete the capital project successfully. This included mapping every installation step, identifying risks, and simulating the plant and new equipment. Before starting any work, foundry engineers modeled the existing space with 3-D scans of the existing footprint. The model was used to examine and validate the new equipment layout, existing equipment and building modifications, and installation access points, as well as confirming equipment fit the space.
The new steel belt conveyor system was somewhat longer than the previous shaker system. To accomplish the installation in record time, plant engineering and maintenance with contractors removed the existing system, which included relocating 25 support beams and corresponding ductwork. In addition, the capital investment plan:
- Removed concrete and cut-in pit access points to remove legacy equipment.
- Modified casting coolers by modifying the ends and moving counterweights.
- Relocated two DIDION Rotary Media Drums® that reclaim core and molding sand from the iron casting manufacturing process.
- Relocated conduit locations and ventilation systems.
- Preassembled the new conveyor system, which arrived in 15 40-foot shipping containers in November of 2023 and was staged outdoors in the sequence in which parts were ultimately installed.